Equipment catalogSilver City Energy Storage Centre
Hydrostor

Silver City Energy Storage Centre

Silver City Energy Storage Centre: safe, reliable, and clean long duration energy storage for New South Wales

StorageCompressed air energy storage plantModelled
Silver City Energy Storage Centre by Hydrostor
Rated power
200MW
Energy capacity
1600MWh
Storage duration
8h

Characteristics

3 of 3 fields · all sourced · retrieved 2026-10-23
Rated power
200MW
Energy capacity
1600MWh
Storage duration
8h

Silver City is a 200 MW / 1,600 MWh Advanced Compressed Air Energy Storage (A-CAES) facility in late-stage development in Broken Hill, New South Wales, providing up to eight hours of long-duration storage. Hydrostor's A-CAES uses grid electricity to compress air, captures the heat in above-ground thermal storage, and stores the compressed air in a purpose-built hard rock cavern held at constant pressure by a water head; on discharge the air is recombined with the stored heat and expanded through a turbine. The project stores excess renewable electricity when transmission capacity is constrained and sends it down the same lines later, and reserves 50 MW / 250 MWh to provide backup power to Broken Hill during network outages. It has received grid connection approval from AEMO and Transgrid, holds a Network Service Agreement with Transgrid and a Long-Term Energy Service Agreement from AEMO Services, and has a project design life of 50+ years.

Manufacturer datasheet (18)

Technology
Advanced Compressed Air Energy Storage (A-CAES)
Project design life
50+ yearsyears
Location
Broken Hill, NSW, Australia
Owner
Hydrostor
Application
Renewables Integration, Non-Network Transmission Reliability Solution
Development status
under late-stage development
Construction employment
Up to 750 full-time equivalent job years during constructionFTE job years
Expenditure in New South Wales
AUD$550 millionAUD
Local expenditure (Broken Hill)
40% (or AUD$240+ million)AUD
Backup capacity reserved
50 MW / 250 MWhMW / MWh
Grid connection approval
grid connection approval from the Australian Energy Market Operator (AEMO) and Transgrid
Grid compliance
meets Generator Performance Standards
Site
adjacent to the Potosi Mine in Broken Hill
Jobs during construction
more than 700 jobsjobs
Jobs during operation
up to 35 jobsjobs
Homes supplied when fully charged
more than 80,000 homes for a dayhomes
Grid agreements
Network Service Agreement with Transgrid and a Long-Term Energy Service Agreement (LTESA) from AEMO Services
Funding
Australian Renewable Energy Agency (ARENA) as part of ARENA’s Advancing Renewables Program