Carrington is Highview's liquid air energy storage plant at Trafford Low Carbon Energy Park near Manchester, designed to provide both energy shifting and grid stability services from a single, zero-carbon source. The plant will deliver 300 MWh of storage and an output of 50 MW for six hours, connecting to existing substation and transmission infrastructure. It includes a stability island, the Phase 1 grid stabilisation component, which will supply synchronous inertia, dynamic voltage support, short-circuit strength and fast frequency response. The LAES system captures excess renewable energy when demand is low, stores it as liquid air, and expands the air to generate electricity when needed. Highview states that LAES can operate without degradation for 40 to 50 years and is fully locatable and modular.

Manufacturer datasheet (10)

Project designation
GEN01X
Site
Trafford Energy Park near Manchester
Project status
Now under construction
Phase 1 (stability island) commissioning
operational from 2026
Grid stability services
synchronous inertia, dynamic voltage support, short‑circuit strength and fast frequency response
Homes served
approximately 480,000 homeshomes
Grid connection
will connect to existing substation and transmission infrastructure in the local area
Groundbreaking date
21 November 2025
Funding raised to build the plant
£300 millionGBP
Investors
National Wealth Fund, Centrica, and a syndicate of investors including Rio Tinto, Goldman Sachs, KIRKBI and Mosaic Capital