Energy mass balanceCostingEquipment sizingStorage
Liquid air energy storage (LAES) plant levelized cost of storage
Liquid air energy storage plant: LCOS in EUR/MWh delivered from separate liquefier, turbine and tank costs (Gøtske et al. 2023 overnight literature cost, linear in capacity as in the source), round-trip efficiency from academic and vendor bases with optional waste heat, cycles capped by recharge time, and the gap to Carrington and Hunterston costs.
- CurrencyEUR 2025
- Battery limitinstalled
- 56 documented assumptions
- Updated27 Oct 2026
Mass and energy balance
What the asset draws and delivers for the case and load you choose.
Reference case
Full charge-discharge cycles you want a year. No grounded default: 300 is a project assumption for near-daily cycling. The plant cannot do more than the clock allows (charge plus discharge time), so above about 10 h the achieved cycles fall below the request. The slider starts at 200; below it the capital and O&M parts grow in inverse proportion to the cycles.
Flows
- In: Electricity for charging—
Asset
Liquid air energy storage (LAES) plant
- Out: Electricity discharged—
Annual quantities at the current usage. Band width: share of energy in; non-energy flows are not to scale.
Electrical output of the expansion turbines. The catalogue binds products here: Highview Carrington is 50 MW for 300 MWh (6 h). The liquefier is sized at the same power (Gøtske et al. use one cost for charge and discharge). Costs are linear in capacity, as in Gøtske et al. 2023: power changes the totals, not the cost per kWh.
- Energy capacity
- — MWh
- Charge (liquefier) power
- — MW
- Energy delivered
- — MWh/year
CAPEX
Specific cost at this size, what backs it, and how it behaves with scale.
Specific CAPEX at this size
—
Reference size 50 MW
Gøtske et al. 2023 Table 1
Model value: the Gøtske/Gautam overnight literature cost, linear in capacity, installed and without contingency or owner's costs. Customized: your own installed cost per kWh stored, used as is at every size; it is then no longer sourced. Either way project mode adds working capital and contingency. Carrington funding is about 1,181 EUR/kWh, roughly 5.4 times the model at that configuration.
Log in to view this sensitivity chart.
- Ex-factory
- Installed· this figure
- Fully financed
Included
- Equipment
- Installation, civil works and engineering
Not included
- Working capital
- Contingency
Added at project level
- Working capital layer, from the project settings
- Contingency, from the project settings
Project figures
Values passed to project mode when this asset is added to a project.
Liquid air energy storage (LAES) plantConcept sketch, not to scale · drag to rotate
- Electricity for charging in
- —
- Electricity discharged outMain product
- —
- CAPEX to the battery limit
- —
- Fixed O&M
- —
- Variable O&M, excluding feedstocks
- 0 EUR/year
- Asset lifetime
- 30 years
Log in to add this asset to a project.
Levelised cost of storage
A standalone indicator for a quick read. Project mode recomputes it for the whole system.
—
- LCOS: capital—
- LCOS: fixed O&M—
- LCOS: charging electricity—
Linked to the balance above
Full charge-discharge cycles you want a year. No grounded default: 300 is a project assumption for near-daily cycling. The plant cannot do more than the clock allows (charge plus discharge time), so above about 10 h the achieved cycles fall below the request. The slider starts at 200; below it the capital and O&M parts grow in inverse proportion to the cycles.
Hours of discharge at rated power; energy capacity = power x duration. Tanks are cheap (31 EUR/kWh) and turbomachinery expensive (562 EUR/kW per side), so long durations cost less per kWh. Carrington is 6 h, Hunterston 12.5 h. Recharge takes duration / RTE, which limits the cycles a year at long durations.
Share of the reheating at discharge supplied by free external low-grade heat (a nearby plant). 0 % = standalone. 100 % = the middle of Highview's 70-80 % claim (75 %), a vendor claim not independently verified. Linear in between, which is a model assumption. The heat is taken as free.
Average price of the electricity bought to charge. Project assumption: no grounded European off-peak price is cited. Divided by the round-trip efficiency in the LCOS, so at 50 % RTE each 10 EUR/MWh adds about 20 EUR/MWh delivered.
Rate of the capital recovery factor over the 30-year life. Default 7 %, Gøtske et al. 2023. Read as real, because every cost is in constant money with no escalation.
Log in to view this sensitivity chart.
Benchmarks
This model's figures against published references and reference cases.
Levelised cost of storage, EUR/MWh
53.1 Cetegen et al. 2025, converted
215.9 Xie et al. 2019, converted
666.9 Xie et al. 2019, converted
CAPEX per kWh stored, EUR/kWh
181.4 Mersch et al. 2026, converted
307.1 Derived from NPM 2024
1,181 Derived from The Chemical Engineer 2024
Reference cases at this size and usage
Log in to compare the reference cases.
All results
Every model output at the current settings, grouped, with the sensitivity charts.
57 outputs · 6 groups · 12 also shown above, dimmed
Levelised cost
8- Capital share of LCOS
- Computing%
- LCOS at the Gøtske 7 % rate
- ComputingEUR/MWh
- LCOS at Carrington CAPEX level
- ComputingEUR/MWh
Size and CAPEX
10- Literature CAPEX per kWh
- ComputingEUR/kWh
- Size factor on CAPEX
- Computingratio
- Power-related CAPEX
- ComputingEUR
- Energy-related CAPEX
- ComputingEUR
- Power share of CAPEX
- Computing%
- CAPEX per kW of discharge
- ComputingEUR/kW
Efficiency
11- Round-trip efficiency
- Computing%
- Round-trip efficiency with standing loss
- Computing%
- RTE of the basis without waste heat
- Computing%
- Discharge efficiency of the basis
- Computing%
- Discharge efficiency with waste heat
- Computing%
- Discharge efficiency at full waste heat
- Computing%
- Output attributable to waste heat
- Computing%
- Academic standalone RTE (reference)
- Computing%
- Highview standalone RTE (reference)
- Computing%
- Highview RTE with waste heat (reference)
- Computing%
- Discharge efficiency implied by the 80 % claim
- Computing%
Energy balance and duty
13- Energy charged
- ComputingMWh/year
- Electricity in per MWh delivered
- ComputingMWh/MWh
- Cycles achieved a year
- Computingcycles/year
- Maximum cycles a year
- Computingcycles/year
- Charge time per cycle
- Computingh
- Discharge hours a year
- Computingh/year
- Charge hours a year
- Computingh/year
- Discharge capacity factor
- Computing%
- Holding time per cycle
- Computingh
- Standing loss per cycle
- Computing%
- Standing loss penalty on charging
- Computingratio
Published references
10- Carrington funding per kWh
- ComputingEUR/kWh
- Model CAPEX at 50 MW, 6 h
- ComputingEUR/kWh
- Carrington / model CAPEX
- Computingratio
- Hunterston planned cost per kWh
- ComputingEUR/kWh
- Model CAPEX at 200 MW, 12.5 h
- ComputingEUR/kWh
- Hunterston / model CAPEX
- Computingratio
- Xie et al. LCOS, low scenario
- ComputingEUR/MWh
- Xie et al. LCOS, high scenario
- ComputingEUR/MWh
- Xie et al. LCOS at 60 % RTE, upper
- ComputingEUR/MWh
- Cetegen et al. LCOS
- ComputingEUR/MWh
Finance and yearly costs
5- Capital recovery factor
- Computing1/year
- Annualised CAPEX
- ComputingEUR/year
- Charging electricity cost
- ComputingEUR/year
- Total annual cost
- ComputingEUR/year
Sensitivities
6 chartsLog in to view this sensitivity chart.
Log in to view this sensitivity chart.
Log in to view this sensitivity chart.
Log in to view this sensitivity chart.
Log in to view this sensitivity chart.
Log in to view this sensitivity chart.
Sources
56 documented assumptions · 8 sources
- arxiv.orgGøtske, Andresen, Victoria (2023), PRX Energy 2, 023006 — LAES costs and efficiencies (Table 1), lifetime, FOM and discount rate (Sec. III.4)
- scholar.xjtu.edu.cnMersch et al. (2026), J. Energy Storage 152, 120580 — optimised LAES cost 205 $/kWh at 100 MW (benchmark only)
- imeche.orgIMechE news (2012), Highview explains liquid air plans — 55-60 % standalone, 70-80 % with waste heat (vendor)
- thechemicalengineer.comThe Chemical Engineer (2024) — Carrington 50 MW / 300 MWh, GBP 300m funding
- newprojectmedia.comNew Project Media — Hunterston 200 MW / 2.5 GWh, GBP 650m expected cost
- research.birmingham.ac.ukXie et al. (2019), Energy Procedia 158 — LAES LCOS GBP 191-590/MWh
- thechemicalengineer.comThe Chemical Engineer (2025) on Cetegen et al., Energy — LAES LCOS about US$60/MWh
- data-api.ecb.europa.euECB reference rates GBP/EUR (2018 0.8847, 2024 0.8466) and USD/EUR 2025 (1.1300)
About
Calculator context
About
Calculator context
Liquid air energy storage plant of the Highview Carrington or Hunterston type. In charge, grid electricity liquefies air (compression, cooling with stored cold, expansion); the liquid air waits in low-pressure cryogenic tanks; in discharge it is pumped, evaporated, reheated with stored compression heat (or free external waste heat) and expanded through turbines. You set the discharge power (10 to 300 MW), the duration (4 to 24 h), the cycles you want a year, the efficiency basis and the share of waste heat.
The cost structure is the one of Gøtske et al. 2023: 562 EUR/kW for the liquefier, 562 EUR/kW for the expansion train and 31 EUR/kWh for the tanks, so power is expensive and energy cheap, and the cost per kWh falls fast with duration. It is an overnight technology cost from the literature, installed but without owner's and development costs, first-of-a-kind premium, contingency or financing: a literature cost, not a project cost. The source costs are linear in capacity and carry no plant size, so the model applies no scale law: the cost per kWh depends on duration, not on power. Fixed O&M is 2 % of the power CAPEX and 1 % of the energy CAPEX a year; the CAPEX is annualised over 30 years.
The round-trip efficiency is not settled and the calculator does not settle it. The academic standalone value is 77 % x 65 % = 50.05 %; Highview quoted 55-60 % for a commercial standalone plant and 70-80 % with low-grade waste heat. The model keeps the 77 % liquefier and writes RTE = charge x discharge efficiency in every case. The top of the vendor claim, 80 %, would need a discharge efficiency above 100 % with that liquefier; it is shown, not used. Recharging takes duration / RTE, so a 24-hour plant cannot cycle daily: the cycles you request are capped by the clock.
The capital cost is the weak point. At the Carrington configuration the model gives about 218 EUR/kWh, while the Carrington funding is about 1,181 EUR/kWh (5.4 times, first-of-a-kind and financing included) and the Hunterston projection about 307 EUR/kWh at 200 MW and 12.5 h, 2.5 times the model at that configuration. Both ratios are outputs, and the Customized option takes a quote. At 50 MW, 6 h, 300 cycles, the academic efficiency, 50 EUR/MWh charging and 7 %, the plant costs about 65.5 MEUR and the LCOS is about 172 EUR/MWh, close to 60 % of it charging electricity; at the Carrington cost level it rises to about 491 EUR/MWh. Xie et al. 2019 give 216 to 667 EUR/MWh after currency conversion; Cetegen et al. 2025 about 53. No revenue, tax or subsidy: those belong to project mode, which also adds working capital and contingency on top of this installed CAPEX.
Model
117 variables — inputs, calculations and outputs, with their dependencies.
Model
117 variables — inputs, calculations and outputs, with their dependencies.
| Variable | Value | Unit | Depends on |
|---|---|---|---|
| 50 | MW | — | |
| 6 | h | — | |
| 300 | cycles/year | — | |
| 1 | — | — | |
| 0 | % | — | |
| 0 | — | — | |
| 1180 | EUR/kWh | — | |
| 50 | EUR/MWh | — | |
| 7 | % | — |
| Variable | Formula | Unit | Depends on |
|---|---|---|---|
if((<=)+(<=)+(<=)+(<)+(>)+(<)+(>)+(<)+(>)+(<=)+(<)+(<)+(>)>,,) | bool | ||
* | kW | ||
* | ratio | ||
* | ratio | ||
* | ratio | ||
(**(+*)^)/max((+*)^-,) | 1/year |
| Variable | Formula | Unit | Depends on |
|---|---|---|---|
* | MW | ||
* | MWh | ||
(+)* | % | ||
(+)* | % | ||
** | % | ||
if(==,,/max(,)) | % | ||
/max(,) | % | ||
/max(,) | % | ||
+(-)** | % | ||
** | % | ||
** | % | ||
/max(*,) | h | ||
/max(+,) | cycles/year | ||
min(,) | cycles/year | ||
* | h/year | ||
* | h/year | ||
/* | % | ||
max(/max(,)--,) | h | ||
/(*)* | % | ||
/max(-*,) | ratio | ||
* | MWh/year | ||
/max(,)* | MWh/year | ||
/max(,) | MWh/MWh | ||
/max(,)* | % | ||
- | MWh/year | ||
(-/max(,))* | % | ||
(/)^(-) | ratio | ||
(*+)/max(,)+ | EUR/kWh | ||
clamp(if(>=,,*),,) | EUR/kWh | ||
** | EUR | ||
/max(*,) | EUR/kWh | ||
(*+)/max(,)/max(,)* | % | ||
** | EUR | ||
- | EUR | ||
/max(,) | EUR/kW | ||
if(<,/,(*(+)^)/max((+)^-,)) | 1/year | ||
* | EUR/year | ||
**+** | EUR/year | ||
* | EUR/year | ||
++ | EUR/year | ||
/max(,) | EUR/MWh | ||
/max(,) | EUR/MWh | ||
/max(,) | EUR/MWh | ||
++ | EUR/MWh | ||
/max(,)* | % | ||
(*+)/max(,)+ | EUR/MWh | ||
//(*) | EUR/kWh | ||
((*+)/+)*(/)^(-) | EUR/kWh | ||
/max(,) | ratio | ||
//(*) | EUR/kWh | ||
((*+)/(/)+)*(/)^(-) | EUR/kWh | ||
/max(,) | ratio | ||
(+)*/max(,)+ | EUR/MWh | ||
/ | EUR/MWh | ||
/ | EUR/MWh | ||
/ | EUR/MWh | ||
/ | EUR/MWh |
Assumptions
56 assumptions used in the calculations
Assumptions
56 assumptions used in the calculations
Lower limit in guards.
Market range Exact by definition.
0Numerical constantUnit multiplier in the CRF, guards and Customized switch.
Market range Exact by definition.
1Numerical constantMid-point of a published range.
Market range Exact by definition.
0.5Numerical constantProtects divisions.
Market range Exact by definition.
0Numerical constantPercent to fraction.
Market range Exact by definition.
0.01Numerical constantFraction to percent.
Market range Exact by definition.
100Numerical constantMW to kW.
Market range Exact by definition.
1000Numerical constantMWh to kWh.
Market range Exact by definition.
1000Numerical constantHours in a year.
Market range Exact by definition.
8760Numerical constantHours in a day.
Market range Exact by definition.
24Numerical constantIdentifier of the Gøtske academic efficiency basis.
1SelectorIdentifier of the Highview commercial standalone efficiency basis.
2SelectorLiquefier (charging) cost per kW of electrical input. The source gives no currency year and no plant size.
Market range no independent range cited
562EUR/kWGøtske et al. 2023 Table 1Expansion train (pumps, evaporator, turbines) cost per kW of output.
Market range no independent range cited
562EUR/kWGøtske et al. 2023 Table 1Cryogenic tanks and thermal stores per kWh. A 2023 Energies paper argues tank cost was underestimated in earlier studies (about six times for a 50 MW plant); the Customized option covers that.
Market range no independent range cited
31EUR/kWhGøtske et al. 2023 Table 1Liquefaction side of the round trip; kept in both efficiency bases.
77%Gøtske et al. 2023 Table 1Discharge side of the academic basis; 77 % x 65 % = 50.05 % round trip.
65%Gøtske et al. 2023 Table 1Boil-off of the low-pressure tanks; about 0.2 % per day-long hold.
200daysGøtske et al. 2023 Table 1Physical service life of the plant (conventional turbomachinery and tanks), used both for the annuity and as the asset lifetime exported to project mode.
30yearsGøtske et al. 2023 Sec. III.4Yearly fixed O&M on the power-related CAPEX.
2%Gøtske et al. 2023 Sec. III.4Yearly fixed O&M on the energy-related CAPEX.
1%Gøtske et al. 2023 Sec. III.4Default of the discount rate slider and basis of the reference LCOS at the source's rate.
7%Gøtske et al. 2023Liquefier power / discharge power. Kept at 1 to stay on the cost basis; a larger liquefier would recharge faster and allow more cycles at long durations.
1Gøtske et al. 2023 (cost symmetry)Low end of the vendor standalone figure.
55%IMechE 2012 (vendor)High end of the vendor standalone figure.
60%IMechE 2012 (vendor)Low end of the vendor claim with waste heat; not independently verified.
70%IMechE 2012 (vendor)Top of the vendor claim. Not used as a target: with a 77 % liquefier it implies a 104 % discharge efficiency, shown as a separate output.
80%IMechE 2012 (vendor)Size of the catalogue product; configuration of the Carrington cross-check.
50MWThe Chemical Engineer 2024Stored energy of Carrington.
300MWhThe Chemical Engineer 2024Duration of Carrington.
6hThe Chemical Engineer 2024Funding raised, which includes first-of-a-kind engineering, development and financing: an upper reference for the plant cost.
300000000GBPThe Chemical Engineer 2024Size of Highview's planned commercial plant.
200MWNPM 2024Stored energy of Hunterston (12.5 h).
2500MWhNPM 2024Developer's expected cost before financial close: a projection.
650000000GBPNPM 2024Low LCOS scenario, used as a benchmark after conversion.
191GBP/MWhXie et al. 2019High LCOS scenario.
590GBP/MWhXie et al. 2019Upper LCOS at 60 % round-trip efficiency.
294GBP/MWhXie et al. 2019Optimistic modelled LCOS from market-optimised operation; secondary report of the paper.
60USD/MWhCetegen et al. 2025 via The Chemical EngineerNo economy of scale applied: Gøtske et al. 2023 cost the plant linearly in capacity (per kW for charge and discharge, per kWh for storage, no plant size), and the model keeps the source's linear costs. Mersch et al. 2026 report a lower optimised cost per kWh at 100 MW than at 10 MW but publish no exponent and do not say whether both optima share a duration, so no scale law is derived from them.
Market range no independent LAES scale exponent found
1Gøtske et al. 2023 Table 1Reference size of the size factor. Inert: with an exponent of 1 the factor is 1 at every size, so this value changes no result. Set at the Carrington size of the catalogue product.
50MWThe Chemical Engineer 2024Converts the Xie et al. 2019 GBP figures.
0.8847GBP/EURECBConverts the Carrington (2024) and Hunterston figures.
0.8466GBP/EURECBConverts the Cetegen 2025 and Mersch 2026 benchmark figures (latest full-year rate).
1.13USD/EURECBNumerical guard only.
20EUR/kWhModel guardNumerical guard only.
5000EUR/kWhModel guardLow end of a 25 MW/125 MWh LAES LCOS. Currency conversion only, no inflation adjustment, and an arbitrage-based duty: places the result, does not validate it.
215.9EUR/MWhXie et al. 2019, convertedHigh end of the Xie range.
666.9EUR/MWhXie et al. 2019, convertedOptimistic modelled LCOS with market-optimised operation.
53.1EUR/MWhCetegen et al. 2025, convertedDerived ratio including first-of-a-kind engineering, development and financing: wider boundary than the model CAPEX.
1,181.2EUR/kWhDerived from The Chemical Engineer 2024Developer projection at 200 MW / 12.5 h, before financial close.
307.1EUR/kWhDerived from NPM 2024Optimised LAES cost at 100 MW; duration not stated in the abstract.
181.4EUR/kWhMersch et al. 2026, convertedMethod: Gøtske et al. 2023 storage cost structure (separate charge power, discharge power and energy costs; FOM 2 %/1 %; 30 years). LCOS = (CRF x CAPEX + fixed O&M) / energy delivered + charging cost / energy delivered. Energy delivered = power x duration x achieved cycles; energy charged = delivered / RTE / (1 - standing loss).
—UnspecifiedConstant money with no escalation, annualised at a rate read as real. The currency year of the Gøtske costs is not stated by the source (2025 assumptions); benchmarks in other currencies are converted at ECB rates without inflation adjustment and are therefore indicative.
—UnspecifiedThe round-trip efficiency is not settled: 50.05 % academic (Gøtske), 55-60 % vendor standalone, 70-80 % vendor with waste heat (IMechE 2012). The model always writes RTE = charge efficiency x discharge efficiency, keeps the 77 % liquefier, and shows each published figure as a separate reference output.
—UnspecifiedThe model CAPEX is an overnight literature cost, not a project cost: it is 5.4 times below the Carrington funding per kWh at the same configuration and 2.5 times below the Hunterston projection. Carrington includes first-of-a-kind and financing; Hunterston is a projection. The gap is published as outputs, and the Customized option lets you use a quote.
—UnspecifiedProject mode chains the charging electricity (inlet, priced by the project) and the discharged electricity (main outlet). Fixed O&M is exported undiscounted; no variable O&M is booked so charging is never paid twice. External waste heat is assumed free and is not a flow.
—Unspecified