High-head reservoir hydropower plant (Francis / Pelton)

Storage hydropower with a reservoir and penstock, 100-1 300 m head, 10-700 MW: turbine chosen by head, water-to-wire efficiency from components, generation from the capacity factor and the inflow it requires, peak-hour share, IRENA cost cases with a sourced size law or your own quote, O&M and LCOE in EUR 2023.

  • CurrencyEUR 2023
  • Battery limitfully financed
  • 74 documented assumptions
  • Updated27 Oct 2026

Mass and energy balance

What the asset draws and delivers for the case and load you choose.

Reference case

Annual generation as a percent of capacity x 8 760 h, the figure IRENA publishes and project mode chains. Default 52.95 %, the IRENA 2023 global weighted average of new hydropower (53 %). Accepted range 25-90 % (IRENA 2012, large hydro). The calculator returns the inflow this generation requires: compare it with the site hydrology.

Flows

    Asset

    High-head reservoir hydropower plant

    • Out: Electricity (net)—

    Annual quantities at the current usage.

    Rated electrical output of the generating units, 10-700 MW. The specific cost follows ORNL's new-site law, cost proportional to P^0.975: x1.059 per kW at 10 MW and x0.953 at 700 MW against the 100 MW reference. At a given capacity factor the generation grows with the capacity, so the LCOE falls only by that 2.5 % slope. Above 700 MW IRENA sees economies of scale that this law does not reproduce, so larger plants are refused.

    Design flow
    — m3/s
    Annual generation
    — MWh/year
    Required annual inflow
    — hm3/year
    Net head
    — m

    CAPEX

    Specific cost at this size, what backs it, and how it behaves with scale.

    Specific CAPEX at this size

    —

    Reference size 100 MW

    ORNL/TM-2015/14 Table 13

    Model value: the reference case, scaled to the capacity with the ORNL exponent 0.975. Customized: the value below is used as entered at every capacity, with no scaling, and is no longer a sourced figure. Fixed O&M stays 2.2 % of it.

    Specific installed cost by installed capacity

    Log in to view this sensitivity chart.

    1. Ex-factory
    2. Installed
    3. Fully financed· this figure
    CAPEX at the battery limit—

    Included

    • Equipment and installation
    • Indirect and owner's costs
    • Contingency

    Not included

    • Nothing

    Added at project level

    • Nothing: project mode uses the figure as is

    Project figures

    Values passed to project mode when this asset is added to a project.

    Concept sketch, not to scale · drag to rotate

    Electricity (net) outMain product
    —
    CAPEX to the battery limit
    —
    Fixed O&M
    —
    Variable O&M, excluding feedstocks
    0 EUR/year
    Asset lifetime
    30 years

    Log in to add this asset to a project.

    Levelised cost of electricity

    A standalone indicator for a quick read. Project mode recomputes it for the whole system.

    —

    • Capital component—
    • O&M component—

    Linked to the balance above

    Annual generation as a percent of capacity x 8 760 h, the figure IRENA publishes and project mode chains. Default 52.95 %, the IRENA 2023 global weighted average of new hydropower (53 %). Accepted range 25-90 % (IRENA 2012, large hydro). The calculator returns the inflow this generation requires: compare it with the site hydrology.

    Height between the reservoir operating level and the turbine (or tailwater) level. High-head plants: 100 m to ESHA's Pelton limit of 1 300 m. Net head = gross head minus the penstock loss.

    Automatic picks Pelton above 350 m net head and Francis below (ESHA Table 6.3; Francis has the higher best efficiency in the overlap). Francis is accepted only for 25-350 m net head, Pelton for 50-1 300 m.

    Friction loss in the waterway at rated flow, as a percent of gross head. ESHA: a 4 % loss in power is usually acceptable when sizing the penstock; higher values are refused.

    97 % is ESHA's value for a 1 MW generator; large machines exceed 99 % (IPCC SRREN). Values below 97 % are refused.

    Real weighted average cost of capital. IRENA uses 5 % for OECD countries and China and 7.5 % for the rest of the world. All costs are constant 2023 EUR, so the rate must be real.

    Your own estimate, in EUR 2023, of the extra value of one MWh delivered in peak hours (price spread plus ancillary services). Default 0: no grounded 2023 value exists. For orientation, IRENA 2012 quotes USD 0.01-0.05/kWh in 2010 USD (7.5-37.7 EUR2010/MWh), not indexed to 2023.

    Levelised cost of electricity by capacity factor

    Log in to view this sensitivity chart.

    Benchmarks

    This model's figures against published references and reference cases.

    Specific installed cost, EUR/kW

    887.8 IRENA RPGC 2023 Table 7.2

    3,876 IRENA RPGC 2023 Table 7.2

    Levelised cost of electricity, EUR/MWh

    14.8 IRENA RPGC 2023 Ch.7

    52.71 IRENA RPGC 2023 Ch.7

    231.2 IRENA RPGC 2023 Ch.7

    Reference cases at this size and usage

    Log in to compare the reference cases.

    All results

    Every model output at the current settings, grouped, with the sensitivity charts.

    49 outputs · 4 groups · 11 also shown above, dimmed

    Hydraulics and turbine

    12
    Net head
    Computingm
    Penstock head loss
    Computingm
    Turbine selected
    Computingcode
    Turbine efficiency
    Computing%
    Turbine-generator efficiency
    Computing%
    Waterway efficiency
    Computing%
    Water-to-wire efficiency
    Computing%
    Gap to SRREN 90 %
    Computingpp
    Design flow
    Computingm3/s
    Water per MWh, lossless waterway
    Computingm3/MWh
    Water per MWh
    Computingm3/MWh
    Penstock penalty factor
    Computingratio

    Energy and dispatch

    11
    Annual generation
    ComputingMWh/year
    Full-load hours
    Computingh/year
    Required annual inflow
    Computinghm3/year
    Hydraulic and conversion losses
    ComputingMWh/year
    Gap to IRENA 2023 CF
    Computingpp
    Peak share of output
    Computing%
    Peak-hour energy
    ComputingMWh/year
    Off-peak energy
    ComputingMWh/year
    Peak block coverage
    Computing%
    Peak hours per year
    Computingh/year
    Peak premium value
    ComputingEUR/year

    Costs

    18
    Levelised cost of electricity
    ComputingEUR/MWh
    Capital component
    ComputingEUR/MWh
    O&M component
    ComputingEUR/MWh
    Value-adjusted LCOE
    ComputingEUR/MWh
    Specific installed cost
    ComputingEUR/kW
    Reference case cost
    ComputingEUR/kW
    Size factor on specific cost
    Computingratio
    Model specific cost
    ComputingEUR/kW
    Specific cost in USD 2023
    ComputingUSD/kW
    Total installed cost
    ComputingEUR
    Civil works
    ComputingEUR
    Mechanical and electrical
    ComputingEUR
    Annualised capital
    ComputingEUR/year
    Fixed O&M
    ComputingEUR/year
    Total annual cost
    ComputingEUR/year
    Capital recovery factor
    Computing1/year
    LCOE at 5 % WACC
    ComputingEUR/MWh
    LCOE at 7.5 % WACC
    ComputingEUR/MWh

    IRENA references

    8
    IRENA 2023 average cost in EUR
    ComputingEUR/kW
    Cost vs IRENA average
    Computing%
    IRENA 2023 average LCOE
    ComputingEUR/MWh
    LCOE vs IRENA average
    Computing%
    IRENA 2023 project LCOE, low
    ComputingEUR/MWh
    IRENA 2023 project LCOE, high
    ComputingEUR/MWh
    IRENA peak value, low (EUR 2010)
    ComputingEUR/MWh
    IRENA peak value, high (EUR 2010)
    ComputingEUR/MWh

    Sensitivities

    9 charts
    LCOE components vs capacity factor

    Log in to view this sensitivity chart.

    LCOE vs real WACC

    Log in to view this sensitivity chart.

    LCOE vs capacity factor

    Log in to view this sensitivity chart.

    Generation and required inflow vs capacity factor

    Log in to view this sensitivity chart.

    Peak share and peak block coverage vs capacity factor

    Log in to view this sensitivity chart.

    Installed capacity: economy of scale on cost (ORNL exponent 0.975)

    Log in to view this sensitivity chart.

    Efficiency vs penstock head loss

    Log in to view this sensitivity chart.

    Water per MWh vs gross head

    Log in to view this sensitivity chart.

    Value-adjusted LCOE vs peak premium

    Log in to view this sensitivity chart.

    About

    Calculator context

    Screening techno-economics for a high-head storage hydropower plant: a reservoir, a penstock and Francis or Pelton turbines chosen by head. The calculator goes from the installed capacity and capacity factor to net generation, the annual inflow it requires, losses, peak-hour dispatch, capital and O&M cost, and the LCOE. Every money figure is EUR 2023, real, on IRENA's Renewable Power Generation Costs in 2023 conventions: 30-year economic life and a real WACC of 5 % (OECD and China) or 7.5 % (rest of world). IRENA publishes in USD 2023; the calculator converts at the Eurostat 2023 average of 1.0813 USD/EUR and shows that conversion as its own step.

    Hydraulics follow the ESHA guide. Net head = gross head x (1 - penstock loss), with ESHA's 4 % sizing criterion as default and ceiling. The turbine is chosen from ESHA Table 6.3: Pelton above 350 m net head, Francis below (higher best efficiency in the overlap). The user can force a type inside its head range. The water-to-wire efficiency is the product of the components, never a posted total: turbine (ESHA Table 6.7: Francis 94 %, Pelton 90 % or 89 %) x generator (97-99 %, ESHA and IPCC SRREN) x (1 - head loss). At the default 500 m gross head the plant runs a multi-nozzle Pelton at 0.90 x 0.99 x 0.96 = 85.54 %, against SRREN's "about 90 %" water to wire.

    Energy: the capacity factor is the usage input, the figure IRENA publishes and project mode chains; default 52.95 %, IRENA 2023's global weighted average, accepted 25-90 % (IRENA 2012 large hydro). E_gen = P x 8 760 h x CF. The calculator returns the annual inflow this generation requires (E_gen x water per MWh, 398.0 hm3/yr at the default) for the user to compare with the site hydrology, and the hydraulic and conversion losses, E_gen x (1/eta_w2w - 1). The reservoir lets the plant run at full power in the 3 120 weekday peak hours first (ICE Endex 08:00-20:00 block), so 67.3 % of the default output lands in peak hours.

    Costs: three reference cases, all IRENA 2023 total installed cost on the same all-in scope (owner's costs, working capital and interest during construction included), exported with battery_limit 'fully_financed': the 2023 global weighted average USD 2 806/kW (2 595.0 EUR/kW, default) and the 5th and 95th percentiles of the 51-100 MW class over 2000-2023, USD 960 and 4 191/kW. They are percentiles, not projects: a x4.4 spread inside one class, so no single figure is the cost of hydropower. The cost is scaled with capacity as (P/100 MW)^(0.975-1), the capacity exponent of ORNL's 2015 new stream-reach model (17 United States projects, 3-824 MW): x1.059 per kW at 10 MW, x0.953 at 700 MW. 100 MW is an OpenJack reference size; IRENA's average prints none. The ORNL head term is not used: cost does not depend on head here. IRENA finds no strong economies of scale below about 450 MW and clear ones only above 700 MW, hence the 700 MW ceiling. A Customized all-in quote (699-4 575 EUR2023/kW, the extreme percentiles of IRENA Table 7.2 up to 700 MW) replaces the case and is used as entered at every size. Civil works are shown as 70 %, mechanical and electrical as 30 % (IRENA Table 7.1, high-head reservoir storage, Europe 2021), for display only. Fixed O&M is 2.2 %/yr of the installed cost (IEA, cited by IRENA) and includes overhaul and rewinding, not major refurbishment. LCOE = (CRF x CAPEX + O&M) / E_gen. Default: 48.70 EUR2023/MWh at 5 % and 59.7 at 7.5 %. Across the input box it spans about 7.7 to 223 EUR2023/MWh: the bottom, a Customized quote at IRENA's lowest percentile run at 90 %, is below the cheapest project IRENA observed in 2023 (14.8 EUR2023/MWh); the three cases alone stay at or below 200. Cross-check, not a calibration: IRENA's 2023 global average of USD 0.057/kWh is 52.71 EUR2023/MWh, between the default's 5 % and 7.5 % results, as expected for an average that blends both rates and real project mixes.

    Value: an optional user premium (EUR 2023 per peak MWh, default 0) gives a value-adjusted LCOE = LCOE - premium x peak share. IRENA 2012 only says peak and ancillary services are "thought to add" USD 0.01-0.05/kWh, in 2010 USD (7.5-37.7 EUR2010/MWh). That range is shown for orientation, not indexed to 2023, and never used as a default. No grounded peak or off-peak price was found, so absolute revenue is not computed.

    Limits: the required inflow is not checked against a hydrology, and no spill is modelled. Capacity factors below 25 % are refused, although IRENA 2023 Table 7.3 prints a 5th percentile of 16 % for Europe 2016-2023. O&M is a flat 2.2 % (range 2-2.5 %, IRENA 2012); IRENA notes larger projects below 2 % and smaller ones higher, which is not modelled beyond the size law it inherits from the capital cost. Not modelled: seasonal storage limits, environmental-flow scheduling, part-load efficiency, sediment, refurbishment, taxes and grid connection beyond the plant.

    Model

    129 variables — inputs, calculations and outputs, with their dependencies.

    129 variables shown of 129
    VariableValueUnitDepends on
    100MW—
    52.95%—
    1——
    0——
    2595EUR/kW—
    500m—
    0——
    4%—
    99%—
    0.05ratio—
    0EUR/MWh—
    VariableFormulaUnitDepends on
    if((<)+(>)+(<=)+(<)+(>)+(<)+(>)+(<)+(>)+(>=)*((<)+(>))+(<)+(>)+(<)+(>)+(<)+(>)+(*(-*)<)+(*(-*)>)+(==)*(*(-*)>)+(>=)*(*(-*)<)+(<)+(>=)+(<)>,,)bool
    if(==,,if(==,,))USD/kW
    (**(+*)^)/max((+*)^-,)1/year
    (**(+*)^)/max((+*)^-,)1/year
    VariableFormulaUnitDepends on
    *(-*)m
    -m
    if(==,if(>,,),)code
    if(==,,if(==,,))%
    (-*)*%
    **%
    **%
    -pp
    */max(****,)m3/s
    /max(****,)m3/MWh
    /max(-*,)ratio
    *m3/MWh
    ***MWh/year
    */hm3/year
    *(/max(,)-)MWh/year
    -pp
    /max(,)h/year
    **h/year
    min(,*)MWh/year
    -MWh/year
    /max(,)*%
    /max(*,)*%
    if(<,/,(*(+)^)/max((+)^-,))1/year
    /EUR/kW
    (/)^(-)ratio
    clamp(*,/,/)EUR/kW
    if(>=,,)EUR/kW
    **EUR
    **EUR
    -EUR
    /EUR/kW
    *USD/kW
    /max(,)*%
    *EUR/year
    **EUR/year
    +EUR/year
    /max(,)EUR/MWh
    /max(,)EUR/MWh
    /max(,)EUR/MWh
    *(+*)/max(,)EUR/MWh
    *(+*)/max(,)EUR/MWh
    */EUR/MWh
    */EUR/MWh
    */EUR/MWh
    /max(,)*%
    *EUR/year
    -/max(,)EUR/MWh
    */EUR/MWh
    */EUR/MWh

    Assumptions

    74 assumptions used in the calculations

    • Protects divisions; far below any physical value of the model.

      Market range Not applicable.

      0
      OpenJack DSL convention
    • Zero used in the validity guard and the turbine selector.

      Market range Not applicable (exact).

      0
      Numerical constant
    • Unit multiplier used in the head-loss factor, the CRF and the validity guard.

      Market range Not applicable (exact).

      1
      Numerical constant
    • Turns a percent (0-100) into a fraction.

      Market range Not applicable (exact).

      0.011/%
      Numerical constant
    • Turns a fraction into a percent.

      Market range Not applicable (exact).

      100%
      Numerical constant
    • Hours in a non-leap year; base of the capacity factor.

      Market range Not applicable (exact).

      8760h/year
      Numerical constant
    • Converts the installed capacity from MW to kW for the per-kW capital cost.

      Market range Not applicable (exact).

      1000kW/MW
      Numerical constant
    • Converts MW to W in the design-flow equation P = rho g Q H eta.

      Market range Not applicable (exact).

      1000000W/MW
      Numerical constant
    • 1 MWh = 3.6e9 J; turns rho g H V (J) into MWh.

      Market range Not applicable (exact).

      3600000000J/MWh
      Numerical constant
    • 1 hm3 (cubic hectometre, million m3) = 1e6 m3.

      Market range Not applicable (exact).

      1000000m3/hm3
      Numerical constant
    • Turns a USD/kWh figure into USD/MWh.

      Market range Not applicable (exact).

      1000kWh/MWh
      Numerical constant
    • Number of whole weeks used to count the weekday peak block (52 x 5 x 12 = 3120 h).

      Market range Not applicable (exact).

      52weeks/year
      Numerical constant
    • Reference size Pref of specific_capex_scaled = case cost x (P/Pref)^(0.975-1). IRENA's 2 806 USD/kW average prints no size: 100 MW is an OpenJack convention, not the size of a cited cost anchor. At 100 MW the size factor is 1, so the three IRENA cases enter unscaled.

      Market range No independent range cited.

      100MW
      OpenJack convention
    • Capital-cost exponent on installed capacity for a new hydropower site. Only the capacity term of the ORNL law is used: its head term (H^-0.120) is not taken, so the cost in this calculator does not depend on head. Evidence medium: 17 United States projects. The capacity slider stops at 700 MW, beyond which IRENA sees economies of scale that 0.975 does not reproduce. Factor x1.059 at 10 MW and x0.953 at 700 MW against 100 MW.

      Market range ORNL NSD alternative models in Appendix A give exponents up to and above 1; no independent range cited.

      0.975
      ORNL/TM-2015/14 Table 13
    • Smallest capacity accepted: the large-hydro cost and capacity-factor basis does not apply to small hydro.

      Market range Not a market value.

      10MW
      IRENA RPGC 2023 / ORNL 2015
    • Largest capacity accepted: above 700 MW IRENA observes economies of scale that the 0.975 exponent does not reproduce.

      Market range Not a market value.

      700MW
      IRENA RPGC 2023 p.156
    • Turbine selector value 0 = automatic choice by net head (ESHA Table 6.3 rule).

      Market range Not applicable.

      0
      OpenJack selector
    • Turbine selector value 1 = Francis.

      Market range Not applicable.

      1
      OpenJack selector
    • Turbine selector value 2 = Pelton with several nozzles.

      Market range Not applicable.

      2
      OpenJack selector
    • Turbine selector value 3 = Pelton with one nozzle.

      Market range Not applicable.

      3
      OpenJack selector
    • Density of turbined water in the hydraulic power and energy equations.

      1000kg/m3
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Gravitational acceleration in P = rho g Q H eta and E = rho g H V.

      9.81m/s2
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Upper limit of the head-loss input (and its default). Above 4 % the input is refused: the ESHA criterion is the only grounded value, and the water-to-wire bounds of this calculator are built on 0-4 %.

      Market range Recommended domain 0-4 % (ESHA sizing criterion).

      4%
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Lowest net head accepted for a Francis turbine; below it the input is refused.

      Market range ESHA Table 6.3: 25-350 m.

      25m
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Automatic selection switches to Pelton above 350 m net head; a Francis forced above it is refused.

      Market range ESHA Table 6.3: 25-350 m.

      350m
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Lowest net head accepted for a Pelton turbine.

      Market range ESHA Table 6.3: 50-1 300 m.

      50m
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Highest net head accepted by the calculator.

      Market range ESHA Table 6.3: 50-1 300 m.

      1300m
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Turbine efficiency when a Francis unit is selected. A best-efficiency value: the reservoir lets the plant run near rated flow, so part-load efficiency is not modelled.

      Market range SRREN: well over 90 % for modern large turbines.

      94%
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Turbine efficiency of a multi-nozzle Pelton unit, the automatic choice above 350 m net head.

      Market range ESHA Table 6.7: 0.89 (1 nozzle) to 0.90 (n nozzles).

      90%
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Turbine efficiency when a single-nozzle Pelton is forced by the user.

      Market range ESHA Table 6.7: 0.89.

      89%
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Upper limit and default of the generator efficiency input (large units).

      Market range 97 % (1 MW, ESHA) to 99 % (large units, SRREN).

      99%
      IPCC SRREN (2011), Chapter 5 Hydropower
    • Lower limit of the generator efficiency input. Lower values are refused: they belong to sub-MW units outside the scope.

      Market range ESHA Table 6.8: 0.970 at 1 MW.

      97%
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • Reference value shown next to the derived water-to-wire efficiency, never substituted for it.

      Market range SRREN: about 90 %.

      90%
      IPCC SRREN (2011), Chapter 5 Hydropower
    • Lowest capacity factor accepted (slider floor). Below 25 % the plant is oversized for the IRENA large-hydro cost basis used here and the input is refused, not priced.

      Market range IRENA 2012: 25-90 % for large hydro. IRENA 2023 Table 7.3 prints a 5th percentile of 16 % for Europe 2016-2023, below this floor: such plants are outside the calculator.

      25%
      IRENA (2012), Renewable Energy Technologies: Cost Analysis Series - Hydropower
    • Highest capacity factor accepted (slider ceiling), a modelling convention from IRENA 2012's large-hydro upper bound, not a measured availability.

      Market range IRENA 2012: 25-90 % for large hydro.

      90%
      IRENA (2012), Renewable Energy Technologies: Cost Analysis Series - Hydropower
    • Reference shown as the gap (percentage points) between the plant's capacity factor and the 2023 global weighted average of new hydropower.

      Market range IRENA 2023: 44 % (2010) to 53 % (2023) global weighted average.

      53%
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Hours of the daily peak block in which a storage plant with at least daily storage concentrates its output.

      Market range Exchange contract definition, no range.

      12h/day
      ICE Endex, French Power Financial Peak Daily Futures, contract specifications
    • Weekdays per week in the peak block. With 52 weeks: 12 x 5 x 52 = 3 120 peak hours a year (derived).

      Market range Exchange contract definition, no range.

      5days/week
      ICE Endex, French Power Financial Peak Daily Futures, contract specifications
    • Cost of the default reference case 'IRENA 2023 global weighted average' (projects commissioned in 2023), kept in USD so the currency conversion is visible as its own step. A capacity-weighted average of many sites, not a typical project: the 51-100 MW class alone spans USD 960-4 191/kW (5th-95th percentile).

      Market range IRENA: most projects 2010-2023 between about USD 500 and 5 000/kW.

      2806USD/kW
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Code of the reference cost case 'IRENA 2023 global weighted average'.

      Market range Not applicable.

      1
      OpenJack selector code
    • Code of the reference cost case 'IRENA 51-100 MW, 5th percentile'.

      Market range Not applicable.

      2
      OpenJack selector code
    • Code of the reference cost case 'IRENA 51-100 MW, 95th percentile'.

      Market range Not applicable.

      3
      OpenJack selector code
    • Cost of the 'low bracket' reference case, in the class that contains the 100 MW reference. 887.8 EUR2023/kW at 1.0813. O&M 2.2 % and the ESHA efficiency chain as in every case; IRENA prints no efficiency.

      Market range IRENA 51-100 MW: USD 960-4 191/kW (5th-95th), weighted average 2 062.

      960USD/kW
      IRENA RPGC 2023 Table 7.2
    • Cost of the 'high bracket' reference case, 3 875.9 EUR2023/kW at 1.0813. The x4.4 spread between the brackets inside one class is why 2 806 USD/kW is never presented as 'the' cost.

      Market range IRENA 51-100 MW: USD 960-4 191/kW (5th-95th).

      4191USD/kW
      IRENA RPGC 2023 Table 7.2
    • Reference mark on the specific cost: IRENA 51-100 MW class, USD 960/kW (5th percentile), in EUR 2023.

      Market range IRENA 51-100 MW: 887.8-3 875.9 EUR2023/kW.

      887.82EUR/kW
      IRENA RPGC 2023 Table 7.2
    • Reference mark on the specific cost: IRENA 51-100 MW class, USD 4 191/kW (95th percentile), in EUR 2023.

      Market range IRENA 51-100 MW: 887.8-3 875.9 EUR2023/kW.

      3,875.89EUR/kW
      IRENA RPGC 2023 Table 7.2
    • Lowest Customized specific cost accepted (slider min and guard).

      Market range IRENA Table 7.2 percentiles, classes up to 700 MW: USD 756-4 947/kW.

      699EUR/kW
      IRENA RPGC 2023 Table 7.2 / Eurostat
    • Highest Customized specific cost accepted (slider max and guard).

      Market range IRENA Table 7.2 percentiles, classes up to 700 MW: USD 756-4 947/kW.

      4575EUR/kW
      IRENA RPGC 2023 Table 7.2 / Eurostat
    • Converts IRENA's 2023 USD figures (capital cost, LCOE references, capex range) into 2023 EUR.

      Market range Annual average; daily rates moved roughly 1.05-1.12 in 2023.

      1.0813USD/EUR
      Eurostat ert_bil_eur_a (Euro/ECU exchange rates, annual data)
    • Upper clamp of the scaled specific capital cost.

      Market range IRENA 2023: about USD 500-5 000/kW.

      5000USD/kW
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Lower clamp of the scaled model cost. Replaces IRENA 2012's USD 1 000/kW (925 EUR/kW), which would have bitten on the 5th percentile case above about 19 MW.

      Market range IRENA 2023: about USD 500-5 000/kW.

      500USD/kW
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Split of the total installed cost into civil works (70 %: dam, reservoir, tunnels, powerhouse) and mechanical plus electrical equipment (10 % + 20 %). Display only: the LCOE uses the total. Applies to the Customized value as well.

      Market range IRENA Table 7.1: 70 / 10 / 20 for high-head reservoir storage; 50 / 30 / 20 for low-head run of river.

      70%
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Fixed O&M as a share of the total installed cost per year. A model value: same in the three cases and under Customized.

      2.2%/year
      IRENA RPGC 2023 Ch.7 (IEA 2010)
    • Annuity period of the capital (CRF). Held fixed so the LCOE stays on IRENA's basis.

      Market range IRENA LCOE convention: 30 years.

      30years
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Used for the reference output 'LCOE at 5 % WACC', which stays on IRENA's OECD/China basis whatever discount rate the user sets.

      Market range IRENA standardised: 5 % (OECD and China) or 7.5 % (rest of world).

      5%
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Used for the reference output 'LCOE at 7.5 % WACC'.

      Market range IRENA standardised: 5 % or 7.5 %.

      7.5%
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Reference shown as 'IRENA 2023 average LCOE' and as the ratio of the plant's LCOE to it.

      Market range IRENA 2023 projects: USD 0.016-0.250/kWh.

      0.057USD/kWh
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Lower end of the observed 2023 project LCOE range, shown as a reference band.

      Market range USD 0.016-0.250/kWh.

      0.016USD/kWh
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Upper end of the observed 2023 project LCOE range, shown as a reference band.

      Market range USD 0.016-0.250/kWh.

      0.25USD/kWh
      IRENA (2024), Renewable Power Generation Costs in 2023
    • Reference mark on the LCOE, EUR 2023 real.

      Market range IRENA 2023 projects: 14.80-231.20 EUR2023/MWh.

      14.8EUR/MWh
      IRENA RPGC 2023 Ch.7
    • Reference mark on the LCOE, EUR 2023 real.

      Market range IRENA 2023 projects: 14.80-231.20 EUR2023/MWh.

      52.71EUR/MWh
      IRENA RPGC 2023 Ch.7
    • Reference mark on the LCOE, EUR 2023 real.

      Market range IRENA 2023 projects: 14.80-231.20 EUR2023/MWh.

      231.2EUR/MWh
      IRENA RPGC 2023 Ch.7
    • Low end of IRENA's peak and ancillary value range, shown in EUR2010/MWh next to the user's premium input.

      Market range USD 0.01-0.05/kWh (2010).

      0.01USD/kWh
      IRENA (2012), Renewable Energy Technologies: Cost Analysis Series - Hydropower
    • High end of IRENA's peak and ancillary value range, shown in EUR2010/MWh.

      Market range USD 0.01-0.05/kWh (2010).

      0.05USD/kWh
      IRENA (2012), Renewable Energy Technologies: Cost Analysis Series - Hydropower
    • Converts IRENA's 2010 USD peak-value range into 2010 EUR.

      Market range Annual average.

      1.3257USD/EUR
      Eurostat ert_bil_eur_a (Euro/ECU exchange rates, annual data)
    • SCOPE. One storage hydropower plant with its own reservoir, a penstock and Francis or Pelton units, high head (100-1 300 m gross). From the natural inflow into the reservoir to net electricity at the generator terminals. Pumped storage, run-of-river without storage, transmission beyond the plant, and reservoir multi-purpose uses (irrigation, flood control) are out of scope.

      Market range Not applicable (scope statement).

      —
      OpenJack scope statement
    • CAPEX BOUNDARY. The capital cost of the three reference cases is IRENA's total installed cost, an all-in figure for commissioned projects (p.155: owner's costs, working capital and interest during construction included). A Customized value must be on the same all-in basis. costs.capex.isbl exports it with battery_limit 'fully_financed', so project mode adds no further cost layers or contingency on top.

      Market range Not applicable (boundary statement).

      —
      IRENA RPGC 2023 Ch.7
    • ECONOMIC BASIS. EUR 2023, real terms, 30-year economic life, real WACC 5 % (OECD/China) or 7.5 % (rest of world), constant annual flows, no tax, no inflation, no fuel. IRENA's USD 2023 figures are converted at the Eurostat 2023 average of 1.0813 USD/EUR (derived step, evidence medium). The exported O&M is an undiscounted annual cash amount in 2023 EUR.

      Market range Not applicable (basis statement).

      —
      IRENA RPGC 2023 Annex I
    • DISPATCH. The reservoir is assumed to hold at least daily-to-weekly storage, so the plant runs at full power in the 3 120 weekday peak hours first and places the remaining energy off-peak: E_peak = min(E_gen, P x 3 120 h). Seasonal storage limits, ramping limits and minimum environmental flows are not modelled.

      Market range Not applicable (assumption).

      —
      OpenJack modelling assumption
    • O&M. 2.2 %/year of the total installed cost, a model value (not an input), also applied to a Customized quote. It covers routine O&M, turbine overhaul and generator rewinding. Major refurbishment is excluded: the 30-year economic life amortises the plant before it is needed (IRENA). Scale: being a share of the scaled capital cost, it already follows the size factor; IRENA p.164 adds that larger projects sit below the 2 % average and smaller ones higher, which this flat 2.2 % does not model.

      Market range 2-2.5 %/year (IRENA 2012, IPCC 2011).

      —
      IRENA RPGC 2023 Ch.7
    • VALUE ADJUSTMENT. The value-adjusted LCOE subtracts a user premium (EUR 2023/MWh of peak energy) weighted by the peak share. The premium defaults to 0. IRENA's order of magnitude for peak plus ancillary value, USD 0.01-0.05/kWh in 2010 USD (7.5-37.7 EUR2010/MWh), is shown as a reference but is NOT indexed to 2023 and is not mixed into the 2023 LCOE.

      Market range IRENA 2012: USD 0.01-0.05/kWh (2010), order of magnitude.

      —
      OpenJack modelling choice
    • TURBINE CHOICE. Automatic: net head above 350 m gives a multi-nozzle Pelton; 25-350 m gives a Francis, whose best efficiency is higher in the overlap. The user may force Pelton in the overlap; a Francis forced above 350 m net head is refused. The turbine type sets only the turbine efficiency.

      Market range Not applicable (rule).

      —
      ESHA (2004), Guide on How to Develop a Small Hydropower Plant
    • INPUT BOX. The box no longer stays inside IRENA's 2023 project range (14.8-231.2 EUR2023/MWh): a Customized quote at IRENA's lowest percentile combined with a 90 % capacity factor gives 7.7 EUR/MWh, below any 2023 project. This is kept, because both ends are observed separately in IRENA's data; the bounds of the LCOE are set on the corner sweep, not on IRENA's range.

      Market range Not a market value.

      —
      OpenJack input box
    • USAGE LEVER. The capacity factor is an input, default 52.95 % (IRENA 2023 global weighted average). The calculator no longer takes an inflow: it returns the required annual inflow (398.0 hm3/yr at the default) for the user to compare with the site hydrology. No spill is modelled.

      Market range IRENA 2012: 25-90 % for large hydro; IRENA 2023 Table 7.3: 16 % (5th percentile, Europe 2016-2023) upward.

      —
      OpenJack default